… meanwhile in Speakman Hall
( Permalink )
2nd Floor Speakman Hallway - ceilings gone!
Work is continuing on installation of pipes for the sprinkler system required by the addition of Alter Hall. While Alter continues to rise, architects and contractors have begun the first phase of renovations to Speakman Hall. Hallway ceilings were removed to locate piping for the sprinklers, and when the installation is complete, Speakman Hall will get new ceilings and lighting that is consistent with the “look” of Alter hallways, contributing to the building of a Fox “complex” … not two different buildings.

John DeAngelo