Where We Are on Friday the 13th

( Permalink )

Foundation walls are nearly completed.  Under drains are almost done. The ramp is gone.  What’s next?  Steel work is scheduled to begin the week of July 16. D’Angelo Bros. returns next week to shape the slabs prior to installing steel.  The plumbers will tie the sanitary lines on the southeast. Once the steel starts, we will all be amazed at how quickly the building will rise.  Here’s what things look like as of 7/13/07  (the day the Phillies try for loss 10,000).

last-wall_small.JPGwest-side_small.JPG